Tetrad May 2025
NavtojAdmin
2025-07-16T06:24:27+00:00
Ongoing Projects
TETRAD
Shenoy Nagar
STILT + 4 FLOORS
8 units
3 bhk
1635 SQFT
May 2025
2nd floor 2A flat skirting chipping work in progress
Staircase first coat putty work in progress
Rain water harvesting earth work in progress
Common Area wiring work in progress
Ring line plumbing work in progress
OHT core packing work in progress ( water proofer)
West side compound wall brick work in progress
Fourth floor wiring work in progress
West side compound wall brick work in progress
First floor sink water line pipe laying work in progress
Third floor rear portion toilet wall tiles fixing work in progress
Page load link
Go to Top
Home
Our Story
Ongoing
Upcoming
Completed
Joint Ventures
Testimonials
More
CAREERS
News & Events
Lets Talk
Menu
Close
Close
Home
About Us
Ongoing
Upcoming
Completed
Joint Venture
Channel Partners
News Events
testimonials
Careers
Contact Us
Call Us
Enquiry
Site Visit
Menu