Tetrad July 2025
NavtojAdmin
2025-08-25T11:20:00+00:00
Ongoing Projects
TETRAD
Shenoy Nagar
STILT + 4 FLOORS
8 units
3 bhk
1635 SQFT
July 2025
Track channel top level plastering work in progress
OHT tiles laying work in progress
Common Area Lighting wiring work in progress
Track channel top level plastering work in progress
East side exterior primer painting work in progress
Parapet wall texture work in progress
Lift Room texture work in progress
Drainage line earth work and pipe laying
EB main cable encasing concrete work in progress
Solar panel fixing done in terrace
Step side putty work in progress
Second floor skirting work in progress
UPVC window sealant filling
Kitchen counter slab measurement taken
Main wiring work in progress
2nd floor 2B flat Marble skirting touch up Plastering work in progress
Main Gate Ramp side brick work in progress
Apex door fixing work in progress
Compound wall electrical lights point work in progress
3rd floor 3A utility tiles laying work in progress
Lift entrance wall plastering work in progress
EB room block work in progress
Third floor front portion second coat putty work in progress
All floors UPVC window fixing work in progress
Kassa door person taken measurements toilet & utility
3rd floor 3A flat second coat putty work in progress
Page load link
Go to Top
Home
Our Story
Ongoing
Upcoming
Completed
Joint Ventures
Testimonials
More
CAREERS
News & Events
Lets Talk
Menu
Close
Close
Home
About Us
Ongoing
Upcoming
Completed
Joint Venture
Channel Partners
News Events
testimonials
Careers
Contact Us
Call Us
Enquiry
Site Visit
Menu