Sai Smrit February 2026
NavtojAdmin
2026-03-23T09:59:59+00:00
Ongoing Projects
Sai Smriti
H Block 15th Main Road
STILT + 5 FLOORS
6 units
4 bhk
2700 SQFT
February 2026
1st floor Utility sunken plastering
First floor toilet sunken waterproof plaster work
4th floor lintel sunshade reinforcement work.
3rd floor ceiling plastering.
Fifth floor roof concrete work in progress
West side External mesh fixing work in progress
Fixing Mesh work west side 3rd floor level.
4th floor front side brick work
East side window border work.
4th floor toilet Wall plastering.
5th floor to terrace steps Brick work.
4th floor Rear portion Lintel RCC.
Page load link
Go to Top
Home
Our Story
Ongoing
Upcoming
Completed
Joint Ventures
Testimonials
More
CAREERS
News & Events
Lets Talk
Menu
Close
Close
Home
About Us
Ongoing
Upcoming
Completed
Joint Venture
Channel Partners
News Events
testimonials
Careers
Contact Us
Call Us
Enquiry
Site Visit
Menu