Brindavanam
H Block Anna Nagar
STILT + 5 FLOORS
8 units
3BHK
1900 SQFT
February 2026
Front wall plastering
Epoxy grout apply 5th floor
4th floor sink cock fixing
5th floor wall texture work
5TH floor main door polishing work
4th floor MCB fixing
East side SETBACK area tile laying
Front elevation wall plastering
5th floor maindoor polish work
5th floor utility sink granite fixing
Metro water connection
Aluminium cladding area wall painting
3rd arch beam chipping
CNG fixing
Duct inner painting
Page load link
Go to Top
Home
Our Story
Ongoing
Upcoming
Completed
Joint Ventures
Testimonials
More
CAREERS
News & Events
Lets Talk
Menu
Close
Close
Home
About Us
Ongoing
Upcoming
Completed
Joint Venture
Channel Partners
News Events
testimonials
Careers
Contact Us
Call Us
Enquiry
Site Visit
Menu